Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm March 20th)
No New Developments since 0:00 pm, 20th March

Unit   Status
1     · Reactor cold shutdown, stable water level, offsite power is
        available.
      · No cooling water is leaked to the reactor containment vessel.
      · Maintain average water temperature below 100°C in the pressure
        restraint.
2     · Reactor cold shutdown, stable water level, offsite power is
        available.
      · No cooling water is leaked to the reactor containment vessel.
      · Maintain average water temperature below 100°C in the pressure
        restraint.
3     · Reactor cold shutdown, stable water level, offsite power is
        available.
      · No cooling water is leaked to the reactor containment vessel.
      · Maintain average water temperature below 100°C in the pressure
        restraint.
4     · Reactor cold shutdown, stable water level, offsite power is
        available.
      · No cooling water is leaked to the reactor containment vessel.
      · Maintain average water temperature below 100°C in the pressure
        restraint.   
other  N.A.

The next information in regard to the plant is planned to be released
at 6:00 pm, 20th March. 