search



Corporate Information

 
Press Release (Apr 06,2011)
Status of TEPCO's Facilities and its services after the Tohoku-Taiheiyou-Oki Earthquake (as of 9:00AM)
Due to the Tohoku-Taiheiyou-Oki Earthquake which occurred on March 11th 
2011, TEPCO's facilities including our nuclear power stations have been 
severely damaged. We deeply apologize for the anxiety and inconvenience 
caused. 

Below is the status of TEPCO's major facilities.
*new items are underlined 
[Nuclear Power Station] Fukushima Daiichi Nuclear Power Station: 
  Units 1 to 3: shutdown due to the earthquake 
  (Units 4 to 6: outage due to regular inspections) 

* The national government has instructed the public to evacuate for those 
local residents within 20km radius of the site periphery and to evacuate 
voluntarily for those local residents between 20km and 30km radius of the 
site periphery.

* Off-site power has been connected to Unit 1 to 6 by March 22, 2011.

* Unit 1
- The explosive sound and white smoke was confirmed near Unit 1 when the 
  big quake occurred at 3:36 pm, March 12th.
- We started injection of sea water at 8:20 pm, March 12th, and then 
  boric acid which absorbs neutron into the reactor afterwards.
- At approximately 2:30 am, March 23rd, we started the injection of sea 
  water into the reactor from feed water system. After that, the injection 
  of freshwater was started from 3:37 pm on March 25th (switched from the 
  seawater injection). At 8:32 am, Mar 29th, transfer from the fire 
  fighting pump to a temporary motor driven pump was made. From 10:42am to 
  11:52am on April 3rd we temporarily switched the pump to the fire 
  fighting pump to inject fresh water to use power through off-site 
  transmission line. We're now injecting fresh water to the reactor by a 
  motor driven pump powered by off-site transmission line.
- At approximately 10:50 am on March 24th, white smoke was confirmed 
  arising from the top of the reactor building.
- At approximately 11:30 am, March 24th, lights in the main control room 
  were restored.
- At approximately 5:00 pm, March 24th, draining water from underground 
  floor of turbine buildings into a condenser was started and it was 
  paused at approximately 7:30 am, March 29th because we confirmed that 
  the water level reached almost full capacity of a condenser. In order 
  to move the water in the condenser into a condensate storage tank, 
  water transfer from the condensate storage tank to suppression pool's 
  water surge-tanks was conducted from around 0:00 pm, March 31st to 3:26 
  pm, April 2nd.
- From 1:03 pm, March 31st, the water spray by the concrete pumping 
  vehicle was started, and finished at 4:04 pm.
- In order to confirm the position of water spray to the spent fuel pool 
  by the concrete pumping vehicle, the water spray was conducted from 5:16 
  pm to 5:19 pm.
- Some of turbine building lights were turned on April 2nd.
- The water transfer from the condenser to the condensate storage tank has 
  been implemented since 1:55 pm, April 3rd.
- As it is suspected that hydrogen gas is accumulated inside reactor 
  containment vessel, we are considering injection of nitrogen gas inside 
  the vessel. 
* Unit 2
- At 1:25 pm, March 14th, since the Reactor Core Isolation Cooling System 
  has failed, it was determined that a specific incident stipulated in 
  Clause 1, Article 15 of Act on Special Measures Concerning Nuclear 
  Emergency Preparedness occurred (failure of reactor cooling function).
  At 5:17 pm, March 14th, while the water level in the reactor reached the 
  top of the fuel rod, we have restarted the water injection with the 
  valve operation.
- At approximately 6:14 am, March 15th, the abnormal sound was confirmed 
  near the suppression chamber and the pressure inside the chamber 
  decreased afterwards. It was determined that there was a possibility 
  that something happened in the suppression chamber. While sea water 
  injection to the reactor continued, TEPCO employees and workers from 
  other companies not in charge of injection work started tentative 
  evacuation to a safe location. 
  Sea water injection to the reactor continued.
- On March 18th, power was delivered up to substation for backup power 
  through offsite transmission line. We completed laying cable further to 
  unit receiving facility in the building, and at 3:46 pm, March 20th the 
  load-side power panel of the receiving facility started to be energized.
- From 3:05 pm to 5:20 pm on March 20th, about 40 tons of seawater was 
  injected into Unit 2 by TEPCO employees.
- At approximately 6:20 pm on March 21st, white smoke was confirmed 
  arising from the top of the reactor building. As of 7:11 am on March 
  22nd, smoke decreased to the level where we could hardly confirm.
- From around 4:00 pm to 5:00 pm on March 22nd, approximately 18 tons of 
  sea water was injected into the spent fuel pool by TEPCO employees. 
- From 10:10 am on March 26th, freshwater (with boric acid) injection was 
  initiated. (switched from the seawater injection) At 6:31pm, March 27th, 
  transfer from the fire fighting pump to a temporary motor driven pump 
  was made. From 10:22am to 0:06pm on April 3rd, we temporarily switched 
  the pump to the fire fighting pump to inject fresh water to use power 
  through off-site transmission line. We're now injecting fresh water to 
  the reactor by a motor driven pump powered by off-site transmission line.
- From 10:30 am on March 25th, seawater injection through Fuel Pool 
  Cooling and Filtering System was initiated. The work was finished at 
  12:19 pm, March 25th. From 4:30 pm, March 29th, freshwater injection 
  through Fuel Pool Cooling and Filtering System was initiated. (We 
  switched from seawater to freshwater). The work was finished at 6:25 pm 
  on March 29th. At 9:25 am, March 30th, we started fresh water injection 
  by a temporary motor driven pump, but we switched the pump to the fire 
  fighting pump due to the pump trouble. At 1:10 pm, March 30th, 
  freshwater injection was suspended, because we found the crack on a part 
  of the hose. At 7:05 pm, March 30th, freshwater injection was resumed 
  and finished at 11:50 pm, March 31. 
- At approximately 4:46 pm, March 26th, lights in the main control room 
  were restored.
- At approximately 4:45 pm, March 29th, the water in a condensate storage 
  tank was being transferred to suppression pool water surge-tanks to 
  prepare for water transfer from a condenser to a condensate storage tank 
  in order to drain water on the underground floor of the turbine building 
  into a condenser. At 11:50 am, April 1st, transfer was completed.
- At 2:56 pm, April 1st, water injection into spent fuel pool in Unit 2 by 
  temporary motor driven pump was initiated. At 5:05 pm on April 1st, the 
  water injection was finished.
- The water transfer from the condenser to the condensate storage tank has 
  been implemented since 5:10 pm, April 2nd.
- Some of turbine building lights were turned on April 2nd.
- At 11:05 am, April 4th, water injection into spent fuel pool in Unit 2 
  by a temporary motor driven pump was initiated. At 1:37 pm, April 4th, 
  the water injection was finished.

* Unit 3
- At 6:50 am, March 14th, while water injection to the reactor was under  
  operation (injection of boric acid was done on Mar 13th), the pressure 
  in the reactor containment vessel increased to 530 kPa. As a result, at 
  7:44 am, it was determined that a specific incident stipulated in the 
  Article 15, the Clause 1 of Act on Special Measures Concerning Nuclear 
  Emergency Preparedness occurred (abnormal increase of the pressure of 
  reactor containment vessel). Afterwards, the pressure gradually 
  decreased (as of 9:05 am, 490 kPa). 
- We continue injecting water into a reactor. (Boric acid was added on March 13)
 * We announced in our past reports that "On March 14, the pressure in the 
   primary containment vessel increased and it was determined that a 
   specific incident stipulated in the Article 15, the Clause 1 of Act on 
   Special Measures Concerning Nuclear Emergency Preparedness occurred". 
   However, we made a mistake in the calculation of the pressure value and 
   the status of Unit 3 did not fall under the above-mentioned specific 
   incidents. We will delete the related description from our latest report.
- At approximately 11:01 am, March 14th, an explosion followed by white 
  smoke occurred near Unit 3. 4 TEPCO employees and 3 workers from other 
  companies (all of them were conscious) sustained injuries and were taken 
  to the hospital by ambulances.
- As the temperature of water in the spent fuel pool rose, spraying water 
  by helicopters with the support of the Self Defense Force was 
  considered. However the operation on March 16th was cancelled.
- At 6:15 am, March 17th, the pressure of the Suppression Chamber 
  temporarily increased, but currently it is stable within a certain 
  range. On March 20th, we were preparing to implement measures to reduce 
  the pressure of the reactor containment vessel (partial discharge of air 
  containing radioactive material to outside) in order to fully secure 
  safety. However, at present, it was not a situation to immediately 
  implement measures and discharge air containing radioactive material to 
  outside. We will continue to monitor the status of the pressure of the 
  reactor containment vessel.
- In order to cool spent fuel pool, water was sprayed by helicopters on 
  March 17th with the cooperation of Self-Defense Forces.
- At approximately past 7:00 pm, March 17th, Self-Defense Forces and the 
  police started spraying water by water cannon trucks upon our request 
  for the cooperation. At 8:09 pm, March 17th, they finished the operation.
- Before 2:00 pm, March 18th, spraying water by fire engines was started 
  with the cooperation of Self-Defense Forces and the United States Armed 
  Forces. At 2:45 pm, March 18th, the operation was finished.
- At approximately 12:30 am, March 19th, spraying water was started with 
  the cooperation of Fire Rescue Task Forces of Tokyo Fire Department. At 
  approximately 1:10 am, March 19th, the operation was finished. They 
  resumed spraying water at 2:10 pm and finished at approximately 3:40 am, 
  March 20th.
- At approximately 9:30 pm, March 20th, spraying water was started with 
  the cooperation of Fire Rescue Task Forces of Tokyo Fire Department. At 
  approximately 3:58 am, March 21st, they the operation was finished.
- At approximately 3:55 pm, March 21st, light gray smoke was confirmed 
  arising from the southeast side of the 5th floor roof of the Unit 3 
  building. The situation was reported to the fire department at 
  approximately 4:21 pm. The parameters of reactor pressure vessel, 
  reactor containment vessel, and monitored environmental data remained 
  stable without significant change. However, employees working around 
  Unit 3 evacuated to a safe location. On March 22nd, the color of smoke 
  changed to somewhat white and it was slowly dissipating.
- At approximately 3:10 pm on March 22nd, spraying water to Unit 3 by 
  Tokyo Fire Department's Hyper Rescue and Osaka City Fire Department was 
  conducted, and completed at approximately 4:00 pm on the same day.
- At approximately 10:45 pm on March 22nd, lights in the main control room 
  were restored.
- At approximately 11:00 am on March 23rd, the injection of sea water to 
  spent fuel pool was conducted, and finished approximately at 1:20 pm on 
  the same day.
- At 4:20 pm on March 23rd, light gray smoke was observed belching from 
  Unit 3 building. The situation was reported to the fire department at 
  4:25 pm on March 23rd. The parameters of the reactor, the reactor 
  containment vessel of Unit 3, and monitored figures around the site's 
  immediate surroundings remained stable without significant change. To 
  be safe, workers in the main control room of Unit 3 and around Unit 3 
  evacuated to a safe location. At approximately 11:30 pm on March 23rd 
  and 4:50 am on March 24th, TEPCO employees confirmed the smoke has 
  disappeared. Accordingly, workers evacuation was lifted.
- From approximately 5:35 am on March 24th, sea water injection through 
  Fuel Pool Cooling and Filtering System was initiated, and finished at 
  approximately 4:05 pm on the same day.
- From 1:28 pm on March 25th, Hyper Rescue team started water spray. The 
  work finished at 4:00 pm on March 25th.
- From 6:02 pm on March 25th, the injection of freshwater to the reactor 
  was started (switched from the seawater injection). At 8:30 pm on March 
  28th, the injection of fresh water was switched to temporary electricity 
  pumps from the fire engine pumps. From 10:03am to 0:16pm on April 3rd, 
  we temporarily switched the pump to the fire fighting pump to inject 
  fresh water to use power through off-site transmission line. We're now 
  injecting fresh water to the reactor by a motor driven pump powered by 
  off-site transmission line.
- At approximately 12:34pm March 27th, the injection of water by the 
  concrete pump truck was started. At approximately 2:36 pm, March 27th, 
  the operation was finished.
- At approximately 2:17pm March 29th, the injection of fresh water by the 
  concrete pump truck was started. (Sea water had been injected so far 
  and transfer from seawater to freshwater was made). The water injection 
  was finished at 6:18 PM, March 29th.
- At approximately 5:40 pm, March 28th, the water in a condensate storage 
  tank was being transferred to suppression pool water surge-tanks to 
  prepare for water transfer from a condenser to a condensate storage tank 
  in order to drain water on the underground floor of the turbine building 
  into a condenser. We finished the transfer work at approximately 8:40 
  am, March 31st.
- From 4:30 pm, March 31st, the water spray by the concrete pumping 
  vehicle was started, and finished at 7:33 pm.
- From 9:52 am, April 2nd, the water spray by the concrete pumping vehicle 
  was started, and finished at 0:54 pm.
- Some of turbine building lights were turned on April 2nd. 
- From 5:03 am, April 4th, the water spray by the concrete pumping vehicle 
  was started, and finished at 07:19 pm.

* Unit 4
- At approximately 6:00 am, March 15th, an explosive sound was heard and 
  the damage in the 5th floor roof of Unit 4 reactor building was 
  confirmed. At 9:38 am, the fire near the north-west part of 4th floor of 
  Unit 4 reactor building was confirmed. At approximately 11:00 am, TEPCO 
  employees confirmed that the fire was out. 
- At approximately 5:45 am on March 16th, a TEPCO employee discovered a 
  fire at the northwest corner of the Nuclear Reactor Building. TEPCO 
  immediately reported this incident to the fire department and the local 
  government and proceeded with the extinction of fire. At approximately 
  6:15 am, TEPCO staff confirmed at the site that there were no signs of 
  fire.
- At approximately 8:21 am on March 20th, spraying water by fire engines 
  was started with the cooperation of Self-Defense Forces and they 
  finished the operation at approximately 9:40 am. At approximately 6:45 
  pm spraying water was started by Self-Defenses' water cannon trucks and 
  finished at approximately 7:45 pm.
- At approximately 6:30 am, March 21st, spraying water by fire engines 
  was started with the cooperation of Self-Defense Forces and the United 
  States Armed Forces. At approximately 8:40 am, March 21, they had 
  finished the operation.
- On March 21st, cabling has been completed from temporary substation to 
  the main power center.
- From approximately 5:20 pm on March 22nd, spraying water from the 
  concrete pumping vehicle was conducted and ended at approximately 8:30 
  pm on the same day.
- From approximately 10:00 am on March 23rd, spraying water from the 
  concrete pumping vehicle was conducted and ended at approximately 1:00 
  pm on the same day.
- From approximately 2:35 pm on March 24th, spraying water by the 
  concrete pumping vehicle was conducted and ended at approximately 5:30 
  pm on the same day.
- From 6:05 am on March 25th, seawater injection through Fuel Pool Cooling 
  and Filtering System was initiated and finished at approximately 10:20 
  am on the same day.
- From 7:05 pm on March 25th, water spray by the concrete pumping vehicle 
  was started and finished at 10:07 pm on March 25th.
- From 4:55 pm on March 27th, water spray by the concrete pumping vehicle 
  was started and finished at 7:25 pm on March 27th.
- At approximately 11:50 am on March 29th, lights in the main control room 
  were restored.
- From 2:04 pm on March 30th, water spray by the concrete pumping vehicle 
  was started and finished at 6:33 pm on March 30th.
- Some of turbine building lights were turned on March 31st.
- From 8:28 am, April 1st, the water spray by the concrete pumping vehicle 
  was started. At 2:14 pm, the water spray finished.
- From 5:14 pm, April 3rd, the water spray by the concrete pumping vehicle 
  was started. At 10:16 pm, the water spray finished.
- From 5:35 pm, April 5th, the water spray by the concrete pumping vehicle  
  was started. At 6:22 pm, the water spray finished. 
* Unit 5 and 6
- At 5:00 am on March 19th, we started the Residual Heat Removal System 
  Pump (C) of Unit 5 in order to cool the spent fuel pool. At 10:14 pm, 
  we started the Residual Heat Removal System Pump (B) of Unit 6 in order 
  to cool the spent fuel pool.
- Unit 5 has been in reactor cold shutdown since 2:30 pm on March 20th. 
  Unit 6 has been in reactor cold shutdown since 7:27 pm on March 20th.
- At Units 5 and 6, in order to prevent hydrogen gas from accumulating 
  within the buildings, we have made three holes on the roof of the 
  reactor building for each unit.
- At approximately 5:24 pm on March 23rd, the temporary Residual Heat 
  Removal System Seawater Pump automatically stopped when its power source 
  was switched. We restarted the pump at around 4:14 pm, March 24th, and 
  resumed cooling of reactor at around 4:35 pm.

* On March 18th, regarding the spent fuel in the common spent fuel pool, 
we have confirmed that the water level of the pool was secured. At around 
10:37 am March 21st, water spraying to common spent fuel pool and finished 
at 3:30 pm. At around 6:05 pm, fuel pool cooling pump was started to cool 
the pool.
  * common spent fuel pool: a spent fuel pool for common use set in a 
    separate building in a plant site in order to preserve spent fuel 
    which are transferred from the spent fuel pool in each Unit building.

* On March 17th, we patrolled buildings for dry casks and found no signs 
of abnormal situation for the casks by visual observation. A detailed 
inspection was under preparation.
 * dry cask: a measure to store spent fuel in a dry storage casks in 
   storages. Fukushima Daiichi Nuclear Power Station started to utilize 
   the measure from August 1995.

* On March 21st, 23rd to April 4th we detected technetium, cobalt, iodine, 
cesium, tellurium, barium, lanthanum and molybdenum from the seawater 
around the discharge canal of the station. (We are reevaluating)

* On March 20th, 21st, 23rd to 30th, we detected iodine, cesium, tellurium 
and ruthenium in the air collected at the site of Fukushima Daiichi 
Nuclear Power Station. (We are reevaluating)

* Plutonium has been detected from the sample of soil at the site of 
Fukushima Daiichi Nuclear Power Station collected on 21st and 22nd of 
March, Concentration level of Plutonium detected was same as that of 
under usual environment and it was thought not to be harmful to human 
health. We will strengthen environmental monitoring of power station and 
surrounding environment.

* We detected radioactive materials contained in the puddles found in the 
turbine building of Unit 1 to 4.

* At approximately 3:30 pm, March 27th, we found water pooling in the 
vertical shaft of the trench outside of the turbine buildings for Units 
1 to 3. The radiation dose at the surface of the water amounted 0.4 mSv/h 
in Unit 1 and over 1,000mSv/h in Unit 2. We could not confirm the amount 
of the radiation dose in Unit 3. We will keep observing the condition of 
the water in the vertical shaft.
On March 29th, we detected niobium, tellurium, ruthenium, silver, 
tellurium, iodine, cesium, and ruthenium in the water collected at the 
trench of unit 1.
On March 30th, we took samples from the water in the trench of Unit 2 and 
3, and conducted nuclide analysis on them. We are now confirming the 
results of the analysis.

* At approximately 9:30 am, April 2nd, we found that there was water in 
the shaft for storing power cable (concrete product) near the intake of 
water for Unit 2, the radioactive air dose was over 1,000mSv/h and the 
water spilled into the sea from the crack (approximately 20 cm) on the 
side of the shaft. We injected fresh concrete to the shaft twice, however, 
we could not observe a change in the amount of water flowing into the sea. 
Therefore, we considered that a new method of stopping the water and 
determined to use the polymer. Necessary equipment and experts of water 
shutoff will be dispatched to the site and after checking the condition, 
we began to stop water shutoff and were injecting polymer on April 3rd. 
On April 4th, we injected the tracer from the vertical shaft of the trench 
to start to examine the water current. We did not observe reduction of 
flow or change of color or water leaking. We checked the diagram and 
confirmed the route. At the same time, we checked the situation of the 
pit in detail and considered the possibility that the water was not from 
the pit, rather, from the joint between the piping upstream of the pit and 
the duct, then the water seeped through a layer of gravel below the 
piping. In order to stop that seepage from the layer of gravel, we decided 
to conduct the water sealing to the bedrock around the piping. We arranged 
for the specialist and gathered equipments. On April 5th, liquid glass was 
injected to the bedrock. Tracer was put through the two new holes drilled 
near the pit to investigate the water flow. At 2:15 pm, April 5th, it was 
observed the water with tracer came out from the crack on the concrete 
lateral of the pit. At 3:7 pm, April 5th, injection of coagulant from the 
holes was initiated and we have confirmed the outflow from the crack on 
the concrete wall of the pit has stopped at 5:38 am, April 6th. We 
confirmed water level has not been rising in the turbine building of unit 
 2. Additional countermeasure to prevent discharge of radioactive material 
from the pit will be implemented. Iodine and Cesium were detected from the 
water sampled in the pit and in the sea near the water discharge. 
Additional nuclide analysis will be implemented.
In addition, from April 2nd, we will implement sampling at 15km offshore 
Fukushima Daiichi and Fukushima Daini Nuclear Power Stations and will 
evaluate these samples comprehensively. 

* Since approximately 9:20 am, March 31st, the water transfer from the 
vertical shaft of Unit 1 to the reservoir of the centralized environmental 
facility was conducted. We finished the task around 11:25 am of the same 
day.

* We found a puddle of water at the main building of the centralized 
environmental facility process. We analyzed and detected approximately 
1.2 x 101Bq/cm3 of radioactivity in full dose in the Controlled Area and 
2.2 x 101Bq/cm3 in full dose in the Non-Controlled Area on March 29.
From April 3rd, the water level in the trench of Unit 3 increased by 15 
cm. The route is not yet known, but there is a possibility that water in 
the turbine building of Unit 4 may be running to the trench of Unit 3. To 
be safe, at 09:22am, April 4th, we stopped transferring water to the 
turbine building of Unit 4. At this moment, the water level in the trench 
of Unit 3 became stable after stopping the water transfer.

* There is plenty of radioactive wastewater in the turbine buildings. 
Especially, Unit 2's wastewater is very highly radioactive. To store this 
stably, it was decided that this needed to be transferred to the Central 
Radioactive Waste Disposal Facility. However, within that facility, we are 
storing ten thousand tons of low level radioactive wastewater. In order to 
transfer more wastewater, we need to discharge the low level radioactive 
wastewater. In addition, as low radioactive subsurface water is piling up 
in sub-drain pits of Units 5 and 6 and a part of subsurface water is 
running into buildings. We are concerned that important equipment to 
secure the safety of reactors may be submerged.
Based on the Section 1 of the Article 64 of the Nuclear Reactor Regulation 
Law, we have decided to discharge to the sea approximately ten thousand 
tons of the accumulated low level radioactive water and a total of fifteen 
hundred tons of the low level radioactive subsurface water stored in the 
sub drain pits of Unit 5 and 6 as soon as we get ready. 
At 7:03 pm, April 4th. we started discharging the low level radioactive 
wastewater stored in the Central Radioactive Waste Disposal Facility to 
the south of the water discharge canal. By 7:10 pm, we started ten pumps. 
Also, at 09:00 pm, April 4th, we started discharging the low level 
radioactive wastewater stored in the sub drain pits of Unit 5 and 6 by 
using one pump via the water discharge canal of Units 5 and 6. 
We evaluate the impact on the discharge of the low radioactive wastewater 
to the sea as approximately 0.6 mSv per year per an adult if an adult eats 
adjacent fish and seaweeds everyday. The amount (0.6 mSv of effective 
radioactive doses per year) is one-forth of annual radioactive dose to 
which the general public is exposed from nature.

* The first barge of the U.S. Forces with fresh water to be used to cool 
down reactors etc. was towed by a ship of Maritime Self-Defense Force and 
docked at 3:42 pm on March 31st 2011. At approximately 3:58 pm, April 1st, 
we started to replenish filtrate tanks with the fresh water, and finished 
at 4:25 pm. At approximately 10:20 am, April 2nd, we resumed replenishing 
filtrate tanks with the fresh water, and finished at 4:40 pm. The second 
barge of the U.S. Forces with the fresh water towed by the ship of 
Maritime Self-Defense Force came alongside the pier at approximately 9:10 
am, April 2nd. It was in preparation for replenishing filtrate tanks with 
the fresh water. We began to transfer fresh water from the second barge to 
the first barge on April 3rd at 9:52 am and continued until 11:15 am on 
April 3rd.

* At 11:35 am, April 1st, a worker fell into the sea while stepping into 
the ship from the pier during the hose laying work of the barge. Other 
crew immediately rescued the worker. While no injury or contamination was 
confirmed, whole body counter has been implemented to check the 
contamination inside the body just in case. 

* From 3:00 pm, April 1st, we started spraying inhibitor in order to 
prevent diffusion of radioactive materials. This attempt was conducted on 
a trial basis at the mountain side area of the common spent fuel pool in 
the range of 500m2. The spraying finished at 4:05 pm. 

* Monitoring posts (no.1 to no.8) which were installed around the site 
boundary have been restored. We will continue monitoring the measured 
value and make announcements on those values accordingly.
 
* We will continuously endeavor to securing safety, and monitoring of 
the surrounding environment. 
Fukushima Daini Nuclear Power Station: 
  Units 1 to 4: shutdown due to the earthquake 
* The national government has instructed evacuation for those local 
residents within 10km radius of the periphery.

* In order to achieve cold shutdown, reactor cooling function was restored 
and cooling of reactors was conducted. As a result, all reactors achieved 
cold shutdown: Unit 1 at 5:00 pm, March 14th, Unit 2 at 6:00 pm, March 
14th, Unit 3 at 0:15 pm, March 12th, Unit 4 at 7:15 am, March 16th. 

* At 2:30 pm on March 30th, the power source of the residual heat removal 
system (B) to cool the reactor of Unit 1 was secured from an emergency 
power source in addition to an offsite power. This means that all the 
units secure backup power sources (emergency power sources) for the 
residual heat removal system (B).

* Unit 1
As it was confirmed that the temperature of the Emergency Equipment 
Cooling Water System *1 has increased, at 3:20 pm, March 15th, we stopped 
the Residual Heat Removal System (B) for the inspection. Subsequently, 
failure was detected in the power supply facility associated with the 
pumps of the Emergency Equipment Cooling Water System. At 4:25 pm, March 
15th, after replacing the power facility, the pumps and the Residual Heat 
Removal System (B) have been reactivated.

* Unit 4
As it was confirmed that the pressure at the outlet of the pumps of the 
Emergency Equipment Cooling Water System*1 has been decreased, at 8:05 pm, 
March 15th, we stopped the Residual Heat Removal System (B) for the 
inspection. Subsequently, failure was detected in the power supply 
facility associated with the pumps of the Emergency Equipment Cooling 
Water System. At 9:25 pm, March 15th, after replacing the relevant 
facility, the pumps and the Residual Heat Removal System (B) have been 
reactivated.

*1:emergency water system in which cooling water (pure water) circulates 
which exchanged the heat with sea water in order to cool down bearing 
pumps and/or heat exchangers etc. 
Kashiwazaki Kariwa Nuclear Power Station: 
  Units 1, 5, 6, 7: normal operation 
  (Units 2 to 4: outage due to regular inspection) 
[Thermal Power Station] 
- Hirono Thermal Power Station Units 2 and 4: shutdown due to the 
  earthquake
- Hitachinaka Thermal Power Station Unit 1: shutdown due to the earthquake
- Kashima Thermal Power Station Units 2, 3, 5, 6: shutdown due to the 
  earthquake 
[Hydro Power Station] 
- Power supply has returned to normal, but facilities damaged by the 
  earthquake are now being handled in a timely manner. 
[Impacts on Transmission Facilities] 
- Power supply has returned to normal, but facilities damaged by the 
  earthquake are now being handled in a timely manner. 
[Potential Implementation on Planned Rolling Blackouts and Request for 
  Conserving Electricity Consumption] 
- Considering the critical balance of our power supply capacity and 
  expected power demand going forward, in order to avoid unexpected 
  blackout in large areas, TEPCO has been implementing rolling blackout 
  (planned blackout alternates from one area to another) since March 14th. 
  We will make our utmost to secure the stable power supply as early as 
  possible. For customers who will be subject to rolling blackout, please 
  be prepared for the announced blackout periods. Also for customers who 
  are not subject to blackouts, TEPCO appreciates your continuous 
  cooperation in reducing electricity usage by turning of unnecessary 
  lights and electrical equipment. 
[Others] 
- Please do NOT touch cut-off electric wires.
- In order to prevent fire, please make sure to switch off the electric 
  appliances such as hair driers when you leave your house.
- For the customer who has in-house power generation, please secure fuel 
  for generator. 

* Revised past progress 
back to page top


to TOP