search



Corporate Information

 
Press Release (Nov 04,2011)
Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, November 4)
 
On March 11 2011, turbines and reactors of Fukushima Daini Nuclear Power 
Station Units 1 to 4 (Boiling Water Reactors, rated output 1,100 Megawatts) 
that we had been constantly operating at rated thermal output were 
automatically shut down at 2:48 pm due to the Tohoku-Chihou-Taiheiyou-Oki 
Earthquake. 
                                        (previously announced on March 11)

At 7:15 am on March 15, the reactor of Unit 4 achieved cold shutdown. As a 
result, all reactors of Units 1 to 4 at Fukushima Daini Nuclear Power 
Station achieved cold shutdown.
                                        (previously announced on March 15)

As of 3:00 pm on November 4, the reactors of Units 1 to 4 are in cold 
shutdown (please refer to the appendix). We will continue to make our 
endeavors to further stabilize each plant of cold shutdown.

·There is no new information since the last update. 
Appendix: TEPCO Plant Status of Fukushima Daini Nuclear Power Station 
                                                         (PDF 16.1KB) 
back to page top


to TOP