Hirono Thermal Power Station
Location | Hirono Town, Futaba County, Fukushima Prefecture |
Commencement Year | April 1985 (Unit 1) |
Fuel | Heavy oil, Crude oil, Coal |
Total output | 3800MW (Unit1-5) |
Damage on facilities |
Unit 2,4: Shut down due to the earthquake Unit 1,3,5: Planned outage at the time of the earthquake |
Date of re-start operation |
Unit 1: July 3,2011 Unit 2: July 11,2011 Unit 3: July 16,2011 Unit 4: July 14,2011 and Unit 5: June 15,2011 |
Hirono Thermal Power Station consists of oil fired plants (Unit 1 to 4) and coal fired plant (Unit 5) , and it’s total output is 3800MW. The power station is located in the nearest site to the epicenter among our thermal power stations and also had the biggest damage.
On March 11,2011, operating Unit 2 and 4 were shut down due to the earthquake, The power station had big damage such that inside turbine building was flooded and exposed to water by Tsunami, and debris are scattered widely in the site. After tsunami left, workers lost words because there was no power station which was used to be.
But after that the thermal power stations were requested to early re-start of operation as a important pillar to meet peak demand in summer time. Cooperated with Transmission, Distribution and other relating departments in our company, we got together workers at Hirono Power Station and started restoring work with strong mind of “ Get it ready by this summer”.
Manufacturers, general constructors, partner companies and we in a body achieved early restorations in short time by working together with breaking the companies barrier
◆Maximum 2800 workers engaged in restoration works here and there in the site.
◆Revetment facilities was damaged by Tsunami. Waste Water Treatment Facility outside was also flooded.
Hitachinaka Thermal Power Station
Location | Tokai Town, Naka County, Ibaraki Prefecture |
Commencement Year | December, 2003 |
Fuel | Coal |
Total output | 1000MW |
Damage on facilities |
Unit 1: Shut down by the earthquake |
Date of re-start operation | Unit 1: May 15,2011 |
Although Hitachinaka Thermal Power Station had severely damages, it was re-started operation as an important base load power supply in mid May,2011 with some creative measures for coal transfer in the site etc.
◆Approximately 1000 people were temporally evacuated to Turbine floor
from the day of the disaster to next day.
◆The wide area in the site was subsided by the earthquake. The area is used as space for emergency power supply facilities.
Kashima Thermal Power Station
Location | Kamisu City, Ibaraki Prefecture |
Commencement Year | March 1971(Unit 1) |
Fuel | Heavy oil, Crude oil |
Total output | 4400MW (Unit 1 to 6) |
Damage on facilities |
Unit 2,3,5,6: Shut down by the earthquake Unit 1,4: Planned outage at the time of the earthquake |
Date of re-start operation |
Unit 1: May 16,2011 Unit 2: April 7,2011 Unit 3: April 6,2011 Unit 4: April 1,2011 Unit 5: April 8,2011 and Unit 6: April 20,2011 |
In order to meet the re-start timing by school new term, we conducted restoration work around-the-clock on the shortest schedule. After Unit 4 re-started on April 1,2011 we could returned the facilities back to normal one by one.