We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 
Inspection/Restoration Status
 ◇ Inspection and restoration completed between April 17th to April 23rd, 2009 
    (Completed on the following date) 
   - No notable activity during this week. 
 ◇ Inspection and restoration to be commenced between April 24th to April 30th, 2009 
    (To be commenced on the following date) 
   - Unit No.5 House transformer inspection (5A, 5B Carrying in and installation): 
       April 24th 
   - Unit No.5 Seismic reinforcement works (Seismic reinforcement works such as pipe 
     supports): 
       April 27th 
   - Unit No.5 Seismic reinforcement works (Seismic reinforcement works for the fuel 
     handling machine): 
       April 23rd* 
                                               * Work schedules added and altered this week.
 ◇ Work Schedule of Major Inspection/Restoration from April 19th to May 16th, 2009
   - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix*
(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
information reported from April 16th to April 22nd, 2009.
 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|  | 
   <Reports from April 16 to April 22, 2009>
 ◇ Other Findings
   - Nothing to disclose to this week. 

Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 99.6KB)