Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of January 21)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status 

 ◇ Inspection and restoration completed between January 15 to January 21, 2010 
    (Completed on the following date) 

   - Unit 1 Main generator inspection:  
       January 15 
   - Unit 6 General integration inspection:  
       January 19  

 ◇ Inspection and restoration to be commenced between January 22 to January 28, 2010 
    (To be commenced on the following date) 

   - Unit 1 Outdoor duct inspection:  
       January 26 
   - Unit 1 System functional test (Partial interlock functional test of reactor protection system):  
       January 22  
   - Unit 4 500kV power cable inspection (Laying cables):  
       January 27  
   - Unit 5 Fuel-load work (Core status confirmation):  
       January 24  
   - Unit 5 Reactor pressure vessel closure:  
       January 26  
   - Unit 5 Outdoor duct inspection:  
       January 26  
   - Unit 5 System functional test (Reactor shut-down margin inspection): 
       January 25  
   - Unit 6 General integration inspection:  
       January 18*  
                                                    * Work schedule added this week.

 ◇ Work Schedule of Major Inspection/ Restoration from January 17 to February 13, 2010

   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix
(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
 Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
 Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
 information reported from January 14 to January 20, 2010.  

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake) 
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from January 14 to January 20, 2010>
Reports from January 14 to January 20, 2010
◇ Other Findings - Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 78.1KB)