We are announcing the status of major inspections and restoration works and 
non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after 
the Niigata-Chuetsu-Oki Earthquake. 
Inspection/Restoration Status 
 ◇ Inspection and restoration completed between August 27 to September 2, 2010 
    (Completed on the following date) 
   - Unit 3 Seismic reinforcement works (Seismic reinforcement works for reactor 
     building overhead crane): 
       August 27
 ◇ Inspection and restoration to be commenced between September 3 to September 
    9, 2010 
    (To be commenced on the following date) 
   - No notable activity during this week 
 ◇ Work Schedule of Major Inspection and Restoration from August 29 to 
    September 25, 2010
   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
     Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
     Earthquake (during 4 Weeks)                               ...Appendix
(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed 
after the Niigata-Chuetsu-Oki Earthquake
 Based on the "Public Announcement Regarding Nonconformance Found in the 
 Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki 
 Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO) provides 
 this announcement containing incidents information reported from August 26 
 to September 1, 2010. 
 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake) 
 |   | 
    <Reports from August 26 to September 1, 2010 >
 ◇ Other Findings
   - Nothing to disclose to this week.

Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki- 
          Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
          Earthquake (during 4 Weeks)(PDF 90.4KB)