We are announcing the status of major inspections and restoration works 
and non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station 
after the Niigata-Chuetsu-Oki Earthquake. 
Inspection/Restoration Status 
 ◇ Inspection and restoration completed between October 15 to October 
    21, 2010 
    (Completed on the following date) 
   - No notable activity during this week. 
 ◇ Inspection and restoration to be commenced between October 22 to 
    October 28, 2010 
    (To be commenced on the following date) 
   - Unit 4 Seismic reinforcement works (Preparation for seismic 
     reinforcement works such as pipe supports):
       October 25 
 ◇ Work Schedule of Major Inspection and Restoration from October 17 
    to November 13, 2010
   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
     Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
     Earthquake (during 4 Weeks)                               ...Appendix 
(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed 
after the Niigata-Chuetsu-Oki Earthquake
 Based on the "Public Announcement Regarding Nonconformance Found in the 
 Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki 
 Earthquake," the Tokyo Electric Power Company, Incorporated (TEPCO) 
 provides this announcement containing incidents information reported from 
 October 14 to October 20, 2010. 
 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)  |   | 
 
    <Reports from October 14 to October 20, 2010> 
 
 ◇ Other Findings
   - Nothing to disclose to this week. 

Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki- 
          Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
          Earthquake (during 4 Weeks) (PDF 90.4KB)