We are announcing the status of major inspections and restoration works 
and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station 
after the Niigata-Chuetsu-Oki Earthquake. 
Inspection/ Restoration Status 
 ◇ Inspection and restoration completed between June 17 to June 23, 2011 
    (Completed on the following date) 
   - No notable activity during this week. 
 ◇ Inspection and restoration to be commenced between June 24 to June 30, 
    2011 
    (To be commenced on the following date) 
   - Unit 4 Seismic reinforcement (Seismic reinforcement works such as pipe 
     supports; reinforcement work for attached structure of reactor pressure 
     vessel): 
       June 27
 ◇ Work Schedule of Major Inspection and Restoration from June 19 to July 
    16, 2011 
   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
     Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
     Earthquake (during 4 Weeks)                               ...Appendix
(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed 
after the Niigata-Chuetsu-Oki Earthquake
 Based on the "Public Announcement Regarding Nonconformance Found in the 
 Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki 
 Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO) 
 provides this announcement containing incidents information reported from 
 June 16 to June 22, 2011. 
 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|  |  | 
    <Reports from June 16 to June 22, 2011>
 ◇ Other Findings
   - Nothing to disclose to this week.

Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki- 
          Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
          Earthquake (during 4 Weeks) (PDF 68.3KB)