TEPCO has voluntarily settled additional inspections regarding the 
measuring facilities of Units 2, 3 and 4 of the Kashiwazaki-Kariwa Nuclear 
Power Station which are under long-term shutdown, and has set an aim (every 
27 months, every 34 months) for this administration in August 2009. We have 
made an investigation into the major facilities of Units 2, 3 and 4, and 
found out that for many measuring facilities their supposed additional 
inspection was overdue. 
|  |  | 
 
Regarding this matter, on March 9, 2012, we have received an instruction 
document "Responding to insufficient maintenance and control for measuring 
control facilities at Kashiwazaki-Kariwa Nuclear Power Station, Tokyo 
Electric Power Company" from the Nuclear and Industrial Safety Agency 
(NISA) of Ministry of Economy, Trade and Industry, and have prepared for a 
prompt reply. (Provided as a press release on March 9, 2012)
Among the Main measuring facilities, we have inspected all 93 measuring 
facilities classified as (A) in the chart above, and confirmed that all 
facilities either 'had no problem in function' or 'had no effect to the 
safety of the plant', and today we have reported this to the NISA. 
|  |  | 
 
5 measuring facilities that were evaluated as ''no effect to the safety of 
the plant' (1 at unit 1, 2 at unit 3 and 2 at unit 4) among the 8 were all 
the same type flow rate measuring facilities. Since they require exchanges 
of certain expendable supplies for inspection, it is difficult to make 
inspection by dismantling them, but since its structure does not allow 
significant margins of error, we are inspecting and confirming the health 
of them by daily patrols since the latest dismantle.
We will continuously look into the measuring facilities and inspect on 
whether there are facilities that are not planned to be inspected when they 
should be, or facilities that have passed their supposed inspection time, 
and report to NISA by April 9, 2012.
                                                                       End
Attached document: 
Outline of the evaluation regarding the effects on the 
 safety of the plant 
*The attached file titled "Outline of the evaluation regarding the effects 
 on the safety of the plant" is only available in Japanese.
We apologize for any inconvenience this may cause.
*We have provided a Japanese press release version of the instruction 
 document received from NISA. However, at this time we have reserved the 
 right to provide an English version due to potential misunderstandings 
 that may arise from an inaccurate rendering of the original Japanese text. 
 We may provide the English translation that NISA releases in our press 
 releases. However, in principle we would advise you to visit the NISA 