Submission of a Request to Change the Technical Specification for the Nuclear Reactor Facility at Fukushima Daiichi Nuclear Power Station

We have submitted a request to revise the Technical Specification for the Nuclear Reactor Facility* at Fukushima Daiichi Nuclear Power Station to the Nuclear Regulation Authority today in order to reflect the actual operation at the station to the technical specification.

Provided below is the outline of the change to be made.

Since the common use diesel generator B system (Unit 2 reactor B system diesel generator) has been recovered and is now on standby as an emergency power supply, provisions on the operation of the diesel generator will be added to the technical specification. The groups/divisions responsible for equipment management will be partially changed according to the progress of the reliability improvement of the external power supply.

Attachment
"Comparison table of the revision of the technical specification for the nuclear reactor facility at Fukushima Daiichi Nuclear Power Station"(PDF 119KB)

* Technical specification for the nuclear reactor facility
Government-approved fundamental rules for nuclear power station operators to follow in order to maintain safe operation and stable condition of nuclear power stations (including operation management, fuel management, radiation management, emergency measures and equipment/facility management based on the"Policy on the Mid-term Security"), which are stipulated by Article 37 Section 1 of the Act on the Regulations of Nuclear Source Material, Nuclear Fuel Material and Reactors.