Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 24)

Fukushima Daiichi NPS Prompt Report 2013

Fukushima Daiichi NPS Prompt Report (Sep 02, 2013)Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 24)

This is follow-up information on the "water leak at a tank in the H4 area in Fukushima Daiichi Nuclear Power Station" found on August 19.

At 7:44 AM today (on September 2), water transfer from Tank No.3 in Group II to Tank No.10 in Group B, within the H4 area, was restarted after having being temporarily suspended since August 29 due to the approach of Typhoon No.15.

After restarting the transfer, we patrolled the site to check on the transfer conditions, and found no abnormality.

The transfer will be suspended when weather conditions such as rainfall are adverse.