Safety Measures Implementation at Kashiwazaki-Kariwa Nuclear Power Station

Emergency Safety Measures

At Kashiwazaki-Kariwa Nuclear Power Station, emergency safety measures such as securing power supply for emergency use have been implemented for all units.

Photos taken on June 18, 2012
14 Power supply cars

14 Power supply cars

4 Alternative heat exchanger cars

4 Alternative heat exchanger cars

7 Debris removal vehicles (4 Wheel loaders, 3 power shovels)

7 Debris removal vehicles
(4 Wheel loaders, 3 power shovels)

8 Fire engines

8 Fire engines

Freshwater reservoir

Freshwater reservoir*

Freshwater reservoir

Freshwater reservoir*

* As water source diversification measures, reservoir of approx. 20,000t is built.