Safety Measures Implementation at Kashiwazaki-Kariwa Nuclear Power Station
Unit 1-4 (Arahama) Side Seawall Construction
On Unit 1-4 (Arahama) side, reinforced concrete seawalls are being built at 15m above sea level (approx. 10m above ground). Approximately 40% of the construction has been completed as of the end of June.
Seawall construction on Arahama side
Concrete placement for the seawalls on Arahama side
Seawalls on Arahama side
(*Partially completed)
Sectional view of the seawalls on Arahama side
(*Partially completed)