Safety Measures Implementation at Kashiwazaki-Kariwa Nuclear Power Station
Unit 5-7 (Ominato) Side Seawall Construction
On Unit 5-7 (Ominato) side, improved soil seawalls are being built at 15m above sea level (approx. 3m above ground). Approximately 90% of the construction has been completed as of the end of June.
Cement improved soil embankment
Seawall construction on Ominato side