Major Maintenance Plan for the Transmission and Transformation Facilities

Print

As of the end of FY2024

  Project Name Voltage(kV) Scale Start of Operation
Transmission Switch of the connection of Kashima-Kaihin line 275 No4 : 0.2km No4 : Apr 2025
Switch of the connection of Fukushima trunk line, mountain-side line 500 No1 : 1.1km
No2 : 1.1km
No1 : May 2025
No2 : Aug 2025
Additional installation of Chiba-Inzai line 275 No.3 : 10.5km
No.4 : 10.5km
No3 : Feb 2027
No4 : Nov 2025
New installation of Higashishimizu line 275 18.8km
(Including 6.4km of existing)
January 2027
Additional installation of Kita-Musashino line 275 13.9km May 2027
New installation of MS18GHZ051500 access line (tentative name) 275 No1 : 0.1km
No2 : 0.1km
No1 : Aug 2027
No2 : Sep 2027
Updating of Shinjuku line 275 No1:22.1km→21.2km
No2:19.9km→21.2km
No3:19.8km→21.2km
No1 : Aug 2030
No2 : Nov 2032
No3 : Dec 2027
Updating of Higashi-Shinjuku line 275 No2:23.4km→5.0km
No3:23.4km→5.3km
No2 : Nov 2032
No3 : Dec 2027
New installation of Shin-Sodegaura line 500 No1:0.1km
No2:0.1km
No1 : Nov 2028
No2 : May 2029
New installation of G5100026 access line 500 0.5km December 2028
New installation of Jyohoku line 275 20.9km August 2033
Substation Additional installation of transformer (Shin-Toyosu substation) 275/66 300MVA January 2026
Increase in capacity of transformer (Shin-Tokorozawa substation) 500/275 1,000MVA 4B : Apr 2026
5B : Jun 2027
Additional installation of transformer (Chiba-Inzai line) 275/66 600MVA 4B : May 2026
1B : Feb 2027
Additional installation of transformer (Toyooka substation) 275/154 450MVA June 2026
Discontinuance of transformer (Shin-Fuji substation) 275/154 -200MVA October 2026 (Discontinuance)
Increase in capacity of transformer (Naka-Tokyo substation) 275/154 200MVA 1B : Dec 2026
2B : Feb 2027
Increase in capacity of transformer (Koto substation) 275/66 150MVA Janurary 2027
Additional installation of transformer (Shin-Fuji substation) 500/154 750MVA February 2027
Additional installation of transformer (Kita-Sagami substation) 275/66 600MVA June 2027
Increase in capacity of transformer (Kita-Tama substation) 275/66 200MVA 2B : Jun 2027
3B : Jun 2029
Increase in capacity of transformer (Minami-tama substation) 275/66 100MVA June 2027
Increase in capacity of transformer (Toumou substation) 275/66 150MVA November 2027
Increase in capacity of transformer (Boso substation) 275/154 250MVA December 2027
Additional installation of transformer (Keihin substation) 275/154 450MVA March 2028
Discontinuance of transformer (Shin-Tokorozawa substation) 500/275 -1,000MVA March 2028
(Discontinuance)
Additional installation of transformer (Eda substation) 275/66 300MVA June 2028
Additional installation of transformer (Shin-Hanno substation) 500/275 1500MVA March 2029
Increase in capacity of transformer (Kashima substation) 275/66 200MVA 7B : May 2029
8B : May 2030

(Note)

  1. Transmission scale: horizontal distance, Substation scale: increase of output